What JEJ brings to Choate
Grading & earthwork
Mass grading, cut/fill, export/import handling, fine grading, building pads, yard grading, and topsoil stripping.
Storm drainage
HDPE/N12 pipe, drainage structures, tie-ins, roof leaders, dry pond conversion, erosion/BMP coordination.
Water & sewer
PVC sewer, copper/water main, fittings, testing/flushing, and service termination coordination.
Asphalt paving
Mill & overlay, LD/HD pavement sections, patching, ABC stone, markings/striping, binder-index awareness.
Concrete / curb
18-inch standard curb, concrete flatwork allowances, bollards, curb repaint/remove-replace alternates.
Bid discipline
Clear inclusions/exclusions, escalation language, unit rates for changes, and normalized production quantities.
Recent / relevant Choate bid history
Discussion points for the meeting
- JEJ can handle targeted paving packages and broader full-site civil scopes.
- Our pricing is strongest when we can see quantities, geotech, haul/export assumptions, and pavement sections early.
- When we are not selected, feedback on scope gaps vs number helps us become a better Choate partner.
Normalized unit-price signals
| Category | Project | Scope item | Qty | Unit rate | Total |
|---|---|---|---|---|---|
| Asphalt | Subaru initial / Rev 1 | Mill & overlay 1.5" C surface | 15,565 SY | $17.50/SY | $272,388 |
| Asphalt patch | Subaru initial | Asphalt patch @ new concrete | 188 SY | $138.75/SY | $26,085 |
| Asphalt patch | Subaru Rev 1 | Asphalt patch @ new concrete | 188 SY | $76.50/SY | $14,382 |
| Asphalt | Pepsi Harrisburg | HD asphalt: 2" 9.5C + 2" 19.0C + 8" ABC | 6,578 SY | $53.50/SY | $351,923 |
| Asphalt | Spartanburg PDI | LD asphalt: 2" C-Sur + 6" ABC | 2,276 SY | $33.00/SY | $75,108 |
| Asphalt | Spartanburg PDI | HD asphalt: 2" C-Sur + 2" C-Int + 8" ABC | 2,674 SY | $55.00/SY | $147,070 |
| Earthwork | Pepsi Harrisburg | Mass grading cut-fill & export onsite | 2,912 CY | $8.25/CY | $24,024 |
| Earthwork | Spartanburg PDI | Mass grading cut-fill — residuum | 3,700 CY | $7.26/CY | $26,862 |
| Earthwork | Spartanburg PDI | Mass grading cut-fill — PWR | 475 CY | $14.13/CY | $6,712 |
| Earthwork | Spartanburg PDI | Export excess overburden | 3,343 CY | $27.76/CY | $92,802 |
| Curb | Pepsi Harrisburg | Curb: 18" standard, no subbase | 1,360 LF | $29.00/LF | $39,440 |
| Curb | Spartanburg PDI | Curb: 18" standard, no subbase | 2,116 LF | $36.00/LF | $76,176 |
| Storm | Spartanburg PDI | 8" & 10" HDPE drainage installation | 475 LF | $52.18/LF | $24,786 |
| Utilities | Spartanburg PDI | 4" PVC sewer + clean-out | 480 LF | $48.04/LF | $23,059 |
| Concrete | Pepsi Harrisburg | HD concrete: 6" concrete + 6" ABC | 11,900 SF | $13.25/SF | $157,675 |
Normalization note: rates are comparable only inside similar scopes. Confirm pavement section, haul/export, subgrade, access, traffic control, schedule, and binder index before applying to another project.
Budget composition highlights
- Pepsi Harrisburg: $565,478 base civil/paving + $260,515 concrete flatwork allowance = $825,993 logged bid value.
- Spartanburg PDI: includes GC, demo, erosion, earthwork, stormwater, wall, asphalt/curb/striping, and sanitary/water scope to $1,130,184 proposal total.
- Subaru Rev 1: $307,020 base paving; optional cement stabilization listed separately at 8,836 SY @ $19.60/SY.
Questions to ask Choate
- Which upcoming opportunities need ROM budgets vs hard bid numbers?
- Where has JEJ been close but not selected — scope gap, schedule, relationship, or number?
- Can JEJ help budget civil alternates as design progresses: export/import, pavement sections, curb/flatwork, storm revisions?
- Can Choate share geotech and early grading models earlier so JEJ can normalize dirt quantities and reduce contingency?